We acknowledge receipt of duly filled applications within seven (7) days). Thereafter, we issue Environmental Impact Assessment (EIA) licenses within 45-90 days as stipulated in the Environmental Impact Assessment/Audit (EIA/EA) Regulations, 2003. Other licenses are issued as per the provisions of the specific regulation.
Cost of Service

Payment of a prescribed fee of 0.1% of the total cost of the project to a minimum of KSh.10,000 with no upper capping is required for the processing of an EIA license. Other fees are stipulated in the relevant regulation.
Customer Obligation

We advise persons intending to undertake development activities to apply for an EIA license at least three months prior to the date they intend to commence the project. This will allow sufficient time for the EIA review process. We also expect proponents to pay the prescribed fees and to secure other relevant government approvals and licenses. We require EIA experts preparing the EIA report to provide accurate information on the proposed project.